Question

A can do a piece of work in 12 days and B can do it in 10 days and A,B and C together in 5 days. C alone can do it in

Answer & Solution

Answer: (Detailed Solution Below)

Option C: 60 days

Detailed Solution:

The correct answer is “60 days”.

The correct answer is: (3) 60 days